Regulatory and permitting risks that could still delay or reshape Energy Transferâs Transwestern DesertâSouthwest pipeline expansion
Regulatory/Permitting Area | What is still required / at risk | Why it matters for the project timeline or scope |
---|---|---|
Federal Energy Regulatory Commission (FERC) â Certificate of Public Convenience & Necessity (CPCN) | ⢠Even after the internal FID, Energy Transfer must still obtain a final FERC âcertificateâ that formally authorises the expansion. ⢠The filing triggers a 30âday ânotice of filingâ and a 30âday âcommentâ period, during which interested parties (state regulators, environmental NGOs, tribal groups, landâowners) can raise objections. |
⢠Any substantive comment or objection can extend the review by months and may force Energy Transfer to modify routing, capacity, or operating standards. |
National Environmental Policy Act (NEPA) â Environmental Impact Statement (EIS) / Environmental Assessment (EA) | ⢠If the project crosses federal lands (e.g., BLMâadministered desert, U.S. Forest Service, or Bureau of Indian Affairs), a NEPA review is mandatory. ⢠The agency (usually BLM or the Department of the Interior) must issue a Record of Decision (ROD) after public scoping, draft and final EIS, and a 30âday public comment period. |
⢠NEPA can uncover previously unâidentified âsignificant impactsâ (e.g., on endangered species, water resources, cultural resources) that may require route changes, additional mitigation measures, or even project redesign. |
Stateâlevel permits (Arizona & New Mexico) | ⢠Arizona: Arizona Corporation Commission (ACC) pipeline safety and siting approvals; Arizona Department of Environmental Quality (ADEQ) airâ and waterâquality permits; state waterâright approvals for any river or aquifer crossings. ⢠NewâŻMexico: New Mexico Public Regulation Commission (PRC) and the Environment Department (NMED) permits; state waterâuse permits; possible âState Environmental Reviewâ (SER) if the project impacts stateâlisted resources. |
⢠State agencies often have separate âpublic interestâ standards and can impose additional mitigation (e.g., stricâer erosionâcontrol, airâemission caps). Delays can arise from parallel stateâlevel environmental reviews, especially if the project triggers the stateâs own NEPAâlike process. |
Bureau of Land Management (BLM) / Federal landâuse authorizations | ⢠Rightâofâway (ROW) on BLMâadministered lands requires a âRightâofâWayâ (ROW) application, environmental analysis, and a âFinding of No Significant Impactâ (FONSI) or a more detailed NEPA review. ⢠If the pipeline traverses tribal lands, the Department of the Interior â Office of Indian Energy and the relevant tribal governments must be consulted and may need to issue TribalâLandâUse permits. |
⢠Federal landâuse approvals can be a bottleneck, especially when the BLM must coordinate with multiple landâuse plans (e.g., Wilderness Areas, National Conservation Areas). Tribal opposition can lead to litigation or the need for additional routing changes. |
Clean Water Act (CWA) â SectionâŻ404 permits (U.S. Army Corps of Engineers) | ⢠Any inâwater work (e.g., river crossings, wetlands disturbance) requires a SectionâŻ404 permit. The Corpsâ âpublic interestâ review includes a 30âday comment period and can be subject to âvetoâ by the EPA if the project is deemed to have unacceptable waterâquality impacts. | ⢠CWA permits can be delayed by âsignificant impactâ findings, especially concerning endangered aquatic species or critical habitats. |
Clean Air Act (CAA) â Emissionâsource permits | ⢠Constructionâârelated emissions (e.g., diesel equipment, fugitive gas releases) and the longâterm operation of compressor stations may need stateâlevel âmajor sourceâ permits and/or EPA âNew Source Reviewâ (NSR) determinations. | ⢠Airâquality modeling disputes can trigger additional mitigation (e.g., lowâNOx equipment) or even limit the size of compressor stations, affecting the projectâs capacity. |
Endangered Species Act (ESA) â Biological Opinions | ⢠If the pipeline corridor intersects known habitats of federally listed species (e.g., desertâbighorn sheep, Mexican grayâwolf, or threatened aquatic species), the U.S. Fish & Wildlife Service (or the National Marine Fisheries Service) must issue a Biological Opinion (BiOp). | ⢠A ânegativeâ BiOp can halt construction until required mitigation (e.g., habitat offsets, timing restrictions) is implemented, potentially altering the alignment or reducing the number of new facilities. |
Culturalâresource and Tribalâconsultation requirements | ⢠SectionâŻ106 of the National Historic Preservation Act (NHPA) requires consultation with the State Historic Preservation Office (SHPO) and potentially with tribal culturalâresource agencies if historic or archaeological sites are present. | ⢠Discovery of a significant site can force a ârouteâchangeâ or extensive mitigation (e.g., dataâcollection, monitoring), adding time and cost. |
Stateâlevel climateâpolicy or ESGârelated reviews | ⢠Both Arizona and NewâŻMexico have enacted âclimateâresilienceâ statutes that may require demonstration that the pipeline will not exacerbate greenhouseâgas emissions beyond stateâset caps. ⢠ESGâscreening by investors (e.g., S&P ESG ratings) can lead to additional disclosure or designâchange requirements. |
⢠Failure to meet emerging climateâpolicy thresholds could result in conditional financing, forcing Energy Transfer to adopt lowerâemission technologies (e.g., electrified compression) that could reshape the project scope. |
Potential litigation / thirdâparty challenges | ⢠Environmental NGOs, landâowner groups, or tribal entities may file lawsuits challenging any of the above permits (e.g., alleging insufficient NEPA analysis, violation of waterârights, or inadequate mitigation). | ⢠Litigation can result in injunctions that stop work, force reâfiling of permits, or demand additional environmental studiesâeach adding months to the schedule and potentially prompting redesign. |
How these risks could translate into project delays or scope changes
Permitâstacking and sequencing â Because multiple agencies (FERC, BLM, EPA, state commissions, tribal governments) must each issue a permit, the overall âcritical pathâ can be extended if any agencyâs review timeline exceeds the projected schedule. A missed or late submission (e.g., an incomplete NEPA scoping document) can add 30â90âŻdays per agency.
Conditional approvals â Agencies often grant permits with âconditionsâ (e.g., additional monitoring, reduced operating pressure, or specific mitigation measures). If the conditions are more stringent than originally planned, Energy Transfer may need to redesign compressor stations, add extra monitoring stations, or even reduce the intended capacityâaltering the original scope.
Routeâchange mandates â Environmental or culturalâresource findings can force the pipeline to be rerouted around a protected habitat or an archaeological site. A reroute can increase the length of the line, add new rightâofâway negotiations, and increase construction costs.
Capacityârestriction requirements â Airâquality or climateâpolicy reviews may limit the maximum allowable throughput, prompting Energy Transfer to reâevaluate the âeconomic supplyâ assumptions that underpinned the FID.
Financing contingencies â Many project financiers (e.g., banks, ESGâfocused investors) attach âpermitâcompletionâ covenants to credit facilities. If a key permit is delayed, lenders may withhold drawâdowns, forcing the developer to seek alternative funding or pause construction.
Bottomâline assessment
- Regulatory risk is still âhighâmediumâ: The FID confirms internal financial approval, but the external permitting pipelineâdominated by FERC, NEPA, state, and federal landâuse approvalsâstill contains several âcriticalâpathâ steps that can each add 3â12âŻmonths of delay if objections, additional studies, or litigation arise.
- Scopeâalteration risk is moderate: Most of the identified permitting risks would first manifest as schedule extensions; however, if a permitting authority imposes substantive environmental or cultural conditions (e.g., mandatory route change, capacity caps, or new mitigation infrastructure), the projectâs original design and economic assumptions could be materially altered.
Key mitigation actions Energy Transfer should prioritize
- Accelerate FERC filing and proactively engage in the 30âday comment window to address likely concerns early.
- Complete NEPA scoping and public outreach with a focus on tribal consultation and endangeredâspecies analysis to reduce the chance of a âsignificant impactâ finding.
- Secure early BLM and state waterâright agreements to avoid later ârightâofâwayâ bottlenecks.
- Develop a robust environmentalâmitigation plan (e.g., habitat offsets, airâemission controls) that can be offered upâfront to regulators and stakeholders.
- Maintain a âcontingencyâ schedule and budget (â10â15âŻ% of total project cost) to absorb potential permitârelated extensions or design modifications.
By addressing these permitting fronts nowâwhile the FID is freshâEnergy Transfer can lower the probability that any remaining regulatory or permitting risk will evolve into a material delay or a fundamental change to the Transwestern DesertâSouthwest pipeline expansion.